Project Update 04/11/2025
From "Gallows Corner"
Go to the project
Hi everyone,
Passengers on public transport passing through the roundabout in the last couple of days may have noticed a slight change in route.
This marks the good progress we have continued to make, completing the first of our two phases of work within the roundabout and meeting the target date for that activity, as established in the latest programme of work. That gang has now moved across to the other stretch of the roundabout to begin our work in this area.
We are also on track to another of those target dates this week, with the work we are currently delivering near the eastern flyover abutment area on the A127. You can see some of the progress in the image alongside this update.
With multiple gangs working at the same time – as well as extra resource being put in place this week – good progress is being maintained, and we continue to work closely with Transport for London (TfL) and the other partners on site to deliver the water main renewal safely and efficiently within that larger project.
Thank you,
The Project Team