Skip to main content

Project Update 06/11/2025

From "Steeple Road Water Mains Renewal"

Go to the project

Hi everyone,

We’re pleased to confirm that the new water main installation within the road closure section of Steeple Road in Latchingdon has been successfully completed. As a result, the road will be re-opened on the afternoon of 6th November, one day ahead of schedule.

While further pipe installation is required to complete the full 3km pipeline scheme, this remaining work will take place entirely within fields. No further road closures will be necessary.

Thank you.

Comments

Commenting is not possible because this project is currently not active.
Total likes: 1, total dislikes: 0
. You can no longer react to ideas in Steeple Road Water Mains Renewal. You can no longer react to ideas in Steeple Road Water Mains Renewal

Share

Current status

Update