Project Update 10/07/2026
From "Layer Treatment Works Enhancements"
Go to the project
Hello Everyone
We've been very busy over the winter and spring seasons, and we've got some good news to share. The major construction phase of the scheme is now complete. The main structure, pipework, and mechanical assets are all now constructed and installed. The next big milestone for the project is the arrival of the electrical panel ready for electrical connections.
We've started the commissioning process as the pipework pressure tests passed and are complete. The process checks are now underway. We're expecting full wet testing to begin over the summer. This involves introducing water into the pipes, and we are to carry our final checks to ensure everything is operating as expected. Once completed, we expect the full filter process to be in service by autumn, mid-September.
We'll update you with our progress in the autumn.
Thanks
The Project Team