Hi everyone,

We have successfully mobilized to commence the gas main crossing works. A secondary visit is required to be undertaken by Cadent Gas which will take place on the 23rd January.

In the meantime, traffic management remains in place with two-way lights, and the permit for these measures has been extended until 30th January.

Next Steps:

  • Complete excavation and prepare for gas supervision visit on 23rd January.

Thank you,