Project Update 14/01/2026
From "Suffolk Mains Renewal, Fressingfield"
Go to the project
Hi everyone,
The team is working in collaboration with Cadent gas under the current two-way lights to cross a high-pressure gas main. A secondary visit is required to excavate with their supervision, which has been scheduled for Friday 23rd January. The two-way lights will remain in place until this work is complete.
Following this, the planned road closure from Monday February 2nd will be in place from the B1116 Mill Lane (Weybread) to Jubilee Corner until August 2026.
Thank you.


Comments
Please to comment.
Total likes: 1, total dislikes: 0
. Sign in to react.
Share
Posted by
Current status
Update