Project Update 17/11/2025
From "Gallows Corner"
Go to the project
Hi everyone,
We just wanted to share a brief update from the project team working on diverting our water main at Gallows Corner.
You may be aware that the existing main sits within the foundations of the flyover, which it predates, so the work being carried out by TFL requires us to carry out this work.
The good news is that we continue to make good progress, in line with the new agreed overall programme, and with multiple teams working concurrently to ensure we deliver this work as safely, efficiently and swiftly as possible. We've been able to keep on programme despite last week encountering another uncharted gas main, which needed careful handling while we worked with the pipe's owners to ensure it was not hazardous.
We will continue to work with TFL and all other partners on site to complete our work in line with the overall flyover project.
Thank you, as always, for your patience and understanding.