Project Update 27/04/2026
From "Gallows Corner"
Go to the project
Hi everyone,
Here's the latest update from our water main diversion at Gallows Corner.
All significant TfL works at Gallows Corner junction are now complete. In recent weeks, Essex & Suffolk Water (ESW) has also completed its construction activities and had begun testing the new water main. The testing process identified some additional work that will be completed this week. Following this, TfL will undertake the final works to allow the road network to fully open.
TfL and ESW are working closely together to assess whether parts of the road could reopen sooner while the remaining work continues. Further safety and technical checks are required before this can be confirmed, and these checks are being carried out as quickly as possible.
We recognise the disruption this work is causing for people travelling through the area, as well as local residents and businesses, and we thank everyone for their continued patience.
Completing this work properly is essential to protecting water supplies in the area. Our teams are working from 7am to 7pm with some extended hours up to 10pm to make sure we complete this as soon as possible.
TfL and ESW remain focused on progressing the remaining work and reopening the road as soon as it is safe to do so.
Thank you, as always, for your continued patience while we carry out this complex work.
