Project Update 28/10/2025
From "Gallows Corner"
Go to the project
Hi everyone,
Good progress continues to be made on site with our water mains renewal.
This week, we anticipate completing the first of the two sections of pipelaying within the roundabout area. The second phase of the roundabout works shall follow on sequentially and is planned to commence next week.
We have also commenced breaking ground for pipelaying at the most south-easterly section of the main, where the second gang continues to make progress.
We are also liaising with TFL regarding a third working area, west of the roundabout, and hope to have that work up and running in the next couple of weeks.
As always, we continue to work closely with TFL and all partners on the site, to ensure we can maintain this good progress, as safely and quickly as possible.
Thank you again for your patience,
The Project Team