Project Update 29 October 2026

From "Aveley Water Pipe Replacement"

Go to the project

Hi everyone,

We’re pleased to let you know that we have now successfully completed the first phase of our pipe renewal work, covering Romford Road, Nethan Drive and Tarmar Drive.

📍 Where we're working now

We’re now progressing with phase two and are making our way along Usk Road. The work is progressing as planned, and we remain on track to finish this phase by the end of December.

📅 Teviot Avenue

Our work on Teviot Avenue has been paused for the time being. We currently plan to return in 2027, with the work requested to take place during the six-week school summer holiday period to help minimise disruption.

We’ll contact residents on Teviot Avenue closer to the time with more information and confirmation of when the work will restart.

💧 Thank you for your patience

We understand that work like this can cause some temporary inconvenience, and we’ll continue to do everything we can to keep disruption to a minimum.

Thank you to everyone in the Aveley community for your continued patience and understanding while we carry out these important improvements. Your support is greatly appreciated, and we look forward to completing the work and delivering the long-term benefits of renewing the local pipe network.

Kind regards,

The Project Team