Project Update 24/03/2026

Community Hub Admin Team •7 months ago Hi everyone,Here’s the latest update from our water main diversion at Gallows Corner.The construction of the connection blocks at the east and west of the site continues this week, with further concrete pours taking place.Work in the drive and reception pits for the earlier tunnelling is now complete and we will complete the reinstatement of those and hand those areas back to Costain later this week.Excavation for the final smaller pipe is complete, and this will be constructed this week ahead of conditioning work to get that pipe ready to be put into use. This will be followed by the work needed to decommission the abandoned element of that distribution main.This will continue to include night time working that requires the area to be lit, for safety purposes, and we appreciate your understanding of the importance of this.Overall, we remain on track for completion within the revised timescale.Thank you as always for your patience.The Project Team

Project Update 18/03/2026

Community Hub Admin Team •7 months ago Hi everyone,We’re continuing our work at Gallows Corner to strengthen local water resilience.Here’s the latest on what’s happening on site, work is ongoing at both the west and east connection pits. On the west side, concrete pours and steelwork are progressing as planned. On the east side, the team is working at full pace with excavation, blinding and the lower base pour completed. The top half will be poured this week , with new parts for the connection to be welded in place.The final distribution main diversion along the A127 Eastbound has begun. To keep disruption to a minimum and accelerate progress, some of this work will take place at night on weekdays and selected weekends throughout March. This activity is focused near local businesses rather than homes.We will continue to keep you updated with our progress.

Project Update 05/12/2025

Community Hub Admin Team •10 months ago Hi everyone,This weekend we are carrying out emergency works that are required on a 12 inch main in Ardleigh Green Road, A127 westbound carriageway. This necessary work has been scheduled over the weekend and overnight to try and curtail the disruption during weekdays. Work will start at 4am, Saturday, 06th of December until late evening, Sunday, 07th of December. A lane closure will be required in order to carry out the works safely. While this work isn’t a result of our project at Gallows Corner, we appreciate the impact of any disruption nearby, and wanted to make you aware of this lane closure. We apologise in advance for the inconvenience caused to drivers and residents during this time.Thank you,The Project Team