Project Update Monday 3 August 2026
Community Hub Admin Team
•
2 weeks ago
🚧 Upcoming Improvement Work in Your AreaWe're writing to let you know that our planned improvement work in your area is about to begin.📍 Site compounds will be set up at: Waterside Car Park: from 3 August 2026 Fisherman's Car Park (Middlemead): from 10 August 2026 🔧 Main project works are scheduled to begin on 14 August 2026.We're working alongside our partner IWS to install new aerators in the reservoir. This forms part of our £2.3 million investment to help maintain a reliable and resilient water supply for the local community.📢 We'll continue to share updates and progress reports through this Community Hub as the project moves forward.❓ If you have any questions or concerns, please get in touch by commenting below and a member of the project team will be happy to help.Thank you for your patience and understanding while we carry out these important improvements.Kind regards,The Project Team
Project Update 28 July 2026
Community Hub Admin Team
•
3 weeks ago
Hi everyone, We are pleased to let you know that Phase One of our work at the Linford Well compound is now complete. Wherever possible, materials from the site have been recycled or reused to reduce waste and support sustainability.All that remains is the installation of a new fence which is currently being manufactured, and we are awaiting delivery. The site continues to be monitored by our security cameras.As part of the ongoing requirements of the Lower Thames Crossing project, we will be returning in September for Phase Two of the works. At this time, there will be minimal impact to local residents.We would like to thank the local community for their patience, understanding, and support while these recent works have been carried out.The Project Team
Project Update Wednesday 22 July 2026
Community Hub Admin Team
•
4 weeks ago
Hello everyone Work on Phase 2 of the Mellis Road pipe replacement project is progressing as planned. This phase runs from Monday 20 July to Monday 31 August 2026, covering the stretch from Mellis Railway Tavern to Judas Lane, including the temporary closure of Thrandeston Road during this period.Our teams are currently installing new, more resilient water pipes to help reduce the risk of future bursts and ensure a reliable supply for customers.To keep everyone safe while we work, a full road closure remains in place. Access for residents is being maintained where possible, and diversion routes are signposted. We appreciate your patience while these essential upgrades take place.Thank you, The Project Team
Project Update Wednesday 22 July 2026
Community Hub Admin Team
•
4 weeks ago
Hi everyone,We've made a good start on site and work is progressing well.The first section of pipework has now been installed, and our team is preparing it for the next stage of the project. We're also getting ready to begin work on the second section later this week.While we wait for additional materials to arrive on site, we're continuing with other preparation work to keep the project moving forward.We're pleased to report that work remains on schedule and everything is progressing as planned.Thank you for your continued patience and support.The Project Team
📢 Join Us Today at Our Drop In Event
Community Hub Admin Team
•
4 weeks ago
📢 Join Us Today at Our Essex & Suffolk Water Drop-In EventWe're looking forward to welcoming you to our community event today at The Fishing Lodge, Hanningfield Waterside Park, Giffords Lane, South Hanningfield Road, Chelmsford, CM3 8HX.💧 This is a great opportunity to learn more about the work we're carrying out at Hanningfield Reservoir, meet members of the project team, and ask any questions you may have.🕑 Drop in anytime between 2:00pm and 6:00pm – there's no need to book.☕ Complimentary tea, coffee, biscuits, and, of course, fresh tap water will be available.🚗 Free parking is available on site.We look forward to seeing you there!
Project Update Tuesday 7 July 2026
Community Hub Admin Team
•
1 month ago
Hi everyone,We wanted to let you know that work has started yesterday.The road closure is now in place and will remain until the work is finished mid-September 2026. We will be working in the Boreham Road area. Our first pipe delivery is schedule for today and once the Heras fencing is in place we will start the trenching operations. We’ll continue to share regular updates on this page so you can keep track of our progress.Thanks for your patience while we carry out these essential improvements to allow for the road widening requirement.
Project Update: Friday 17 July 2026
Community Hub Admin Team
•
4 weeks ago
Hi everyone, Just a friendly reminder that work will be starting in your area from around 8am on Monday. We’ll be beginning on Burnham Road, Bodmin Road (Burnham Rd to Dartmouth Rd), Dartmouth Road, and Totnes Walk. Temporary traffic lights will be in place at various points between Monday 20 July - mid October. We understand that this kind of work can be disruptive, so please be assured we’ll do everything we can to keep any inconvenience to a minimum. You’ll receive a letter around two weeks before we reach your specific street, with more detailed information about what to expect. In the meantime, if you have any questions, please don’t hesitate to get in touch with us via this Community Hub page by leaving a comment below as we’re always happy to help. Thank you,The Project Team
Project Update 08/07/2026
Community Hub Admin Team
•
1 month ago
Hi everyone, The project is progressing really well, and we’re pleased to share that everything remains on track with no issues affecting our schedule. Our teams have been working safely and efficiently, and customers in the area should continue to see steady, well‑managed activity.So far, we’ve installed 4,874 metres of new infrastructure. This is a great milestone and reflects the strong pace of work on site. We’re committed to keeping disruption to a minimum and ensuring customers stay informed as we move through each stage.We’ll continue to provide updates as the project advances, and we appreciate everyone’s patience and support while the improvements are being delivered.Thank you, The Project Team
Project Update 06/07/2026
Community Hub Admin Team
•
1 month ago
Hi everyone, ESW & TfL are working hard to complete the project as soon as possible, while ensuring infrastructure is safe, fully assured and ready to enter service. Complex work remains, but we currently expect to complete our works and hand the site back to TfL by the end of August. Following this, TfL will need to complete final reinstatement and resurfacing works in the area where work has been taking place before they can fully reopen the road network.ESW will continue to carry out our remaining works, which includes complex remedial works in the tunnel and carrying out testing to confirm that the repair is complete.The replacement of a section of pipework is also underway as we shared last week, and testing will be carried out to ensure this has rectified the identified defect.Once the above work has been completed, our final testing and cleansing of the new main will take place, including the final connections to our network. It is at this stage we will hand the site back to TfL.We are very sorry for the ongoing inconvenience caused by these works, which all parties are working to complete with the least possible amount of additional disruption.TfL will provide a final completion date, once they are in a position to do so.You can find the most up to date information from TfL here: Project updates and travel advice.Thank you, The Project Team
Welcome to your Community Hub Page
Community Hub Admin Team
•
2 months ago
👋 Welcome!We would like to introduce a new project at Hanningfield Reservoir and provide an overview of the planned work.🚧 Work is planned to begin in early August 2026 and will include the design, installation, commissioning, and testing of new compressors at Hanningfield Reservoir. This work will help improve the quality of the raw water and support the wider ecosystem within the reservoir 🌿💧📢 As the project progresses, we’ll share regular updates here to keep you informed about what’s happening and what to expect. Your views are really important to us, so we’d love to hear from you.💬 If you have any questions or need any additional support, please leave a comment on this Community Hub page by leaving a comment below and a member of the Project Team will be happy to help.
Project Update 11/06/2026
Community Hub Admin Team
•
2 months ago
Hi everyoneWe’re pleased to share that our Foxes Lane project is progressing well and is now entering its final stage. The next step involves connecting the new water main, which will take place between Monday 15 June and Friday 19 June 2026.To carry out this work safely and efficiently, there will be temporary traffic management measures, including: Two-way traffic lights Reduced speed limits in the immediate area In addition, there will be night-time working on Monday 15 June 2026 to help minimise disruption during busier daytime hours. We will do everything possible to keep noise and disturbance to a minimum during this time.We understand that roadworks can be inconvenient, and we sincerely appreciate your patience and cooperation while we complete these essential improvements. This work will help ensure a more reliable and resilient water supply for the local community.Thank you,The Project Team
You’re Invited: Join Our Community Event! 🎉
Community Hub Admin Team
•
2 months ago
Hi everyone, Just a friendly reminder about our Essex & Suffolk Water customer event on Tuesday 30 June at Springfield Parish Centre, St Augustine's Way, Springfield, Chelmsford, CM1 6GX.It’s your chance to find out what we’re doing in your area and speak to the team.Drop in any time between 1:30pm and 6:00pm — we’d love to see you there!Complimentary tea, coffee, biscuits (and of course, tap water!) will be available, and there is parking in the on-site car park.Thank you, The Project Team
Project Update 25/06/2026
Community Hub Admin Team
•
2 months ago
Hi everyone, We would like to provide an update on the water main diversion at Gallows Corner.We are continuing to progress repair work on the newly installed water main at Gallows Corner. This is a complex repair, and work is already underway within the existing area where there is access to the pipe network. From Saturday 27 June, we will start to remove part of the pipe that needs to be replaced. This work will take place in the current working area next to the roundabout, and no changes are expected to the current road access. Some repair work will also continue underground, as well as off-site work to manufacture the specialist components needed to complete the repair. We are aware that references to a mid-October completion date have been shared online. We are working hard to complete the repairs ahead of this timescale, but we are not yet in a position to confirm a final date and want to avoid sharing information that may later change. We continue to work closely together with TfL and remain focused on completing the remaining works as quickly and safely as possible, restoring full access to the road network and protecting vital water supplies. Thank you, The Project Team
Project Update 12/06/2026
Community Hub Admin Team
•
2 months ago
Hi everyone, We appreciate it has been a little while since we last shared an update with you and we are now in a position to provide you with some additional information on the current status of the programme. We have now completed the testing required to identify the additional areas of work needed on the newly installed water main. This has been a challenging and technically complex process, during which damage to the water main has been identified after the initial installation phase.Work is now already underway to progress the necessary repairs, including sourcing additional materials and mobilising specialist resources. These activities will continue within the existing section of the road where access has already been established to reach the pipes beneath the carriageway. As much of the work will continue to take place underground, specialist teams may not always be visible at street level.Throughout the programme, we have remained focused on carrying out the work safely and efficiently. This approach has been essential in protecting vital water supplies.We will continue to work closely with Transport for London (TfL) and remain focused on completing the remaining works and restoring full access to the road network as quickly as possible.Thank you,The Project Team
Project Update 09/06/2026
Community Hub Admin Team
•
2 months ago
Hi everyone, We’ve been made aware that traffic is building up around the school during drop‑off and pick‑up times, which may be causing delays in the surrounding area.As our works progress along the road, there may be short periods where traffic is heavier than usual. We kindly ask that you allow a little extra time for your journey, particularly during peak times.We appreciate your patience and understanding while we carry out these essential improvements. Thank you, The Project Team
Project Update 08/05/2026
Community Hub Admin Team
•
3 months ago
Good Afternoon,Here is the latest update from our water main diversion at Gallows Corner.Our teams are working extremely hard around the clock to complete testing and commissioning of the water pipe. The fast-paced and significant work the teams have carried out so far means TfL can partially re-open the junction.On Sunday 10 May 2026, Gallows Corner will partially reopen to general traffic.Drivers will be able to travel through the area via: A12 Eastern Avenue eastbound and the roundabout Flyover from A12 Eastern Avenue East to A127 Southend Arterial Road eastbound only Straight Road in both directions and the roundabout Roundabout and A12 Colchester Road eastbound only Main Road in both directions and the roundabout The following roads remain closed to traffic and diversions remain in place: No access from the roundabout onto A12 Eastern Avenue East No access from A12 Colchester Road to the roundabout No access from the roundabout onto A127 Southend Arterial Road No flyover access from A127 Southend Arterial Road to A12 Eastern Avenue East Bus routes via Gallows Corner (routes 174, 496, 498 and 499) may experience delays of up to five minutes. Travel advice Anyone driving through the area should plan ahead and leave more time for their journey Drivers travelling long-distance westbound in the area should continue to re-route via the M25 and use the M11 and A13 to complete their journeys Bus users should plan ahead, allow more time for your journey and check before you travel on TfL’s website. The road network at and around Gallows Corner is expected to be very busy and subject to queues and delays to journeys. Customers who have contacted us via the community hub will receive a response by the end of next week. Thank you again for your patience.
Project Update 21/05/2026
Community Hub Admin Team
•
3 months ago
Hi everyone, Just a quick update as the project is progressing well and we’re starting the next phase at Jubilee Corner.We are putting in new traffic management from Tuesday 26 May 2026. John Shepherd Rd traffic diverted via the War Memorial Access to The Fox & Goose, The Swan and New Street via the War Memorial New Street access also via Laxfield Rd Road between Jubilee Corner and John Shepherd Rd fully closed Even if our teams aren't visible, work is still ongoing behind the scenes to complete the job as safely and efficiently as possible.Thanks for your patience.The Project Team
Project Update 05/02/2026
Community Hub Admin Team
•
7 months ago
Hi everyone, We’re pleased to be getting started in Shoeburyness. Customers in the first phase will receive a letter over the next few days. We have a planned phasing of work in Shoeburyness and will invite customers to take part in the programme as we reach each area. We’ll keep you updated here as the work progresses, and we’ll also share details of any community events here too. Thanks for your patience while we work our way through the area.Thank you,The Project Team
Increased Monitoring on Site - May 2026
Community Hub Admin Team
•
3 months ago
Hi everyone, We’ve recently seen a rise in general antisocial behaviour and speeding in the area around our working site. To make sure our team can continue to work safely, we’ve put some additional monitoring measures in place and are reminding everyone on site to remain alert to their surroundings.These steps are purely precautionary and are part of our standard approach to keeping our people, partners and the wider community safe while we carry out this work.We’ll continue to review the situation and adjust our safety measures as needed throughout the project.Thank you, The Project Team
Traffic Management Update – May 2026
Community Hub Admin Team
•
3 months ago
Hi everyone,We are moving into the next phase of our works in Fressingfield, which includes a hard closure at the War Memorial. This means access arrangements will temporarily change: The Swan – access via the War Memorial The Fox & Goose – access via Jubilee Corner Gatemen are positioned on site to support residents, businesses and deliveries Harleston Hill remains closed while works continue No construction is currently taking place between the War Memorial and Mill Road, but plant movements will continue, so speed restrictions remain in place These arrangements are expected to remain in place until 20 July. Further updates will be issued ahead of the works at Jubilee Corner.We are aware of increased traffic on Church Street and Cratfield Road. “Unsuitable for diversion route” signage will be installed to help manage this.Residents within the next phase of the closure will receive updated letters and access passes.Thank you,The Project Team
Shoeburyness Community Event
Community Hub Admin Team
•
4 months ago
Hello!Come and meet our community engagement team and find out more about our lead pipe replacement project, which is currently in Shoeburyness.Our lead replacement project team is working in your area, renewing our pipework by replacing the communication pipes – which connect our water mains to your water supply pipe.While we’re here, we’re also offering to check and replace your water supply pipe, for free, if it’s made of lead.Got questions or want to sign up?Come and chat with our team. They’re coming to Shoeburyness with our Essex & Suffolk Water van, Sandy.Where: Shoeburyness Community Fire Station, 54 High Street, SS3 9UDWhen: Thursday 7 May, 10.00am – 3.00pmThey’ll explain the work, answer your questions, and help you get a free lead pipe upgrade if your supply pipe needs it. You can also have a chat with them about pretty much anything water-related that’s on your mind.For more information on the project, please visit eswater.co.uk/leadreplacement
Project Update 30/03/2026
Community Hub Admin Team
•
4 months ago
Hi everyone,We’re entering the critical final phases on our water main diversion work at Gallows Corner.At the end of this week, we anticipate starting the commissioning work to ensure that the large main is ready to be connected into the existing main, via the connection points previously installed.This will see the water main undergo final testing for resilience and quality before being put into supply (note: individual sections have been individually tested as they have been built). Should we encounter any concerns, we have time built into our programme to enable us to resolve these.Away from the large pipe, the smaller ‘distribution main’ we have been working on is in the ground and ready to be disinfected and sampled, before going into supply. This means that we are nearing the end of the current period of 24-hour working.Some shorter periods of 24-hour activity may be required at the end of the commissioning of the larger pipe, to restore the working area and grout the old main, as part of its decommissioning. We will let customers living nearby know if and when this will be required.Thank you as always for your patience and understanding while we have worked on this project, within the larger flyover project.The Project Team
Project Update 03/03/2026
Community Hub Admin Team
•
5 months ago
Hi everyone,Despite the exceptionally high rainfall across East Anglia in recent months and with January alone exceeding its average rainfall, our teams continue to make excellent progress on the water main upgrade. To help keep the project on schedule, we’re working on efficiencies by carrying out drilling and open-cut digging simultaneously, allowing us to maintain momentum across different sections of the route.We’ve now installed 1,545m of 180mm pipe, including a complex 72m drill beneath the culvert, with a second drill completing today. We’ve also reinstated 246m of open‑cut trench and excavated a further 100m this week, keeping the project on target.With recent feedback we have been queried on why these works can take time, to help understanding the complexity involved, including road closure restrictions, we are sharing the photos of our latest progress.These photos help show the challenging ground conditions, the careful engineering involved, and the safety measures in place. They give a clearer picture of what’s happening on the ground, including:• Challenging ground conditions and existing utilities we’re working around.• Our drill rig in position completing the culvert drill shot.• The new valve configuration ready for installation near the memorial.• Sections of open‑cut trench that have been foam‑concreted and prepared for reinstatement.• Steel plates being used to safely maintain driveway access.• And the existing water main being replaced.Thank you for your continued support as we deliver this essential upgrade.As part of our ongoing works in the area, we remain committed to maintaining a safe, positive, and respectful environment for both our customers and our workforce.Recently, our team has experienced instances of challenging interactions, including aggressive behaviour from members of the public, which is not acceptable. While we understand that essential works can be disruptive and frustrating, we kindly ask all members of the community to treat our on-site teams with courtesy and respect to ensure we can deliver this project with no delays to our proposed timeframe.Our colleagues are working hard to deliver improvements that will benefit the whole community, and their safety and wellbeing are extremely important to us. We want to ensure they can carry out their duties without feeling unsafe or at risk.We’re now eight weeks into our forty week programme, and we’re pleased to share that installation work is progressing well. We’ve shared new photos to help our community see the scale and complexity of the project, and to give a clearer understanding of why this type of essential work takes time and careful planning.The team is working through challenging ground conditions with the wet weather and navigating around existing utilities, which requires caution and patience. We’ve also listened closely to community feedback and have introduced additional signage, increased updates on our online community hub, and are planning more community drop‑in events to understand how we can support you throughout the works.To keep the project moving efficiently, we are also completing directional drilling and open‑cut excavation simultaneously, supported by extra resource on site.Thank you for your continued cooperation and understanding as we complete these essential works.The Project Team
Project Update 03/03/2026
Community Hub Admin Team
•
5 months ago
Good morning,We’re into March and work continues to progress towards completion of our water mains diversion work at Gallows Corner.Further work is continuing towards the connections within the pits at either end of the tunnelled phase of pipes. Once that is done, these will be refilled.Excavations are also progressing for work on thrust blocks for the main connections on the larger pipe. Thrust blocks are structures that help ensure the stability of the pipes.We have an extra crew joining the team this week, adding to those already on site, to do the final work on the remaining smaller pipe. This will include some night time working, but this will be away from homes and we will monitor noise levels to ensure we remain within permitted levels and minimise disruption.Thank you as always for your patience during this complex project.The Project Team