Gallows Corner

As part of the major improvement works at Gallows Corner Flyover being carried out by Transport for London (TfL) and their main contractor, Costain, we’re taking the opportunity to upgrade one of our older water mains alongside the A127.

Doing this now means we can avoid more disruption and higher costs down the line and most importantly, it helps protect your water supply before the main construction work gets fully underway.

We are working on a diversion and upgrade of the water main whilst Transport For London (TFL) is carrying out its work to renew and strengthen the Gallows Corner flyover.

We will be involved in excavating sections of the road along the north side of the A127.

We understand the effects our activities may have, and we apologise in advance for any inconvenience these essential works may cause but we are committed to minimising any disturbance and disruption to residents and businesses.

Start Date: June 2025

Estimated End Date: Under Review

Partners: Transport for London (TFL), Costain, Galliford Try

FAQs

Open for participation

Phases

Phases overview
Project Updates

Project Updates

12 June 2025 - No end date

Keep up to date with the latest news, progress and upcoming work on our project.

27 issues

Project Update 12/03/2026

Community Hub Admin Team 1 month ago
Total likes: 1, total dislikes: 0
. Sign in to react.
Update
Total likes: 1, total dislikes: 0
. Sign in to react.
Update
Total likes: 1, total dislikes: 0
. Sign in to react.
Update

Project Update 08/01/2026

Community Hub Admin Team 3 months ago
Total likes: 1, total dislikes: 0
. Sign in to react.
Update

Project Update 17/12/2025

Community Hub Admin Team 4 months ago
Total likes: 1, total dislikes: 0
. Sign in to react.
Update