Mundon Pipe Renewal

Project Overview

The Mundon pipe renewal project is a £2 million investment to improve the reliability of the local water network.

We're replacing around 5km of older water mains along parts of Blind Lane, New Hall Lane, Mundon Road and Fambridge Road with new plastic pipes and valves. This work will help improve water quality, reduce leaks and lower the risk of burst pipes.

To minimise disruption, especially for local and seasonal businesses, the work has been scheduled outside the busy summer period.

Once complete, these upgrades will provide a more reliable water supply and help prevent the bursts and leaks that have affected the area in the past.


Phase 1: Blind Lane & New Hall Lane

  • When: : Mid to late September 2026 – January/February
  • Where: Field edges along Blind Lane and New Hall Lane

Phase 2: Mundon Road

When: January/February 2027 – March 2027

Where: Mundon Road (field edges and selected road sections)

Phase 3: Fambridge Road

When: March 2027 – May 2027

Where: Fambridge Road (field edges and selected road sections)

The overall scheme is expected to run until Spring 2027

📅 Start Date: September 2026

📅 Estimated End Date: Spring 2027

Investment Value: £2 Million

Phases

Phases overview

Project Updates

6 August 2026 23:00 - No end date

Keep up to date with the latest news, progress and upcoming work on our project.

0 posts

No results found. Please try a different filter or search term.

Filters

Total posts: 0
There are no projects available.

Sorting changed to: New

No values available.

Selected zero tag filters.