Skip to main content
Essex & Suffolk Water Home

Shingle Hill Mains Upgrade

Shingle Hill Mains Renewal is one of the Suffolk area candidates selected to form apart of our upgrade programme following a history of bursts and evidence of the infrastructure aging and deteriorating.

The scope of works involves upgrading 1km of existing 3", 4" and 6" AC main and communication pipes/boundary boxes which will be our fasted methodology of installation which is directional drilling.

Our planned construction state date will be 23rd February 2026 and will be a 5 week programme, due to complete 27th March 2026.

Start Date: 23rd February 2026

Estimated End Date: 27th March 2026.

Partner: T4 LTD

Investment Value: £130,000

FAQs

Open for participation

Phases

Phases overview
Project Updates

Project Updates

18 February 2026 - No end date

Keep up to date with the latest news, progress and upcoming work on our project.

0 issues

No results found. Please try a different filter or search term.

Filters

Total posts: 0

Sorting changed to: New

No values available.